Q49). An activity is
a).The beginning or end of a specified job
b).An element of work entailed in the project
c).The movement of heavy vehicles from one place to another
d).The progress of work upto a certain limit
Correct Answer:
An element of work entailed in the project
Explanation:
Q50). PERT
a).Provides an approach for keeping planning up to date
b).Provides a way for management to require that planning be done on a uniform and logical basis
c).Permits management to foresee quickly the impact of variations from the plan
d).All of the above
Correct Answer:
All of the above
Explanation: