Q41). A gantt chart indicates

a).Balance of work to be done
b).fficiency of project work
c).Comparison of actual process with the scheduled progress
d).Progress cost of project

Correct Answer:
Comparison of actual process with the scheduled progress
Explanation:



Q42). The jobs going ahead of schedule are conveniently shown in

a).Gantt chart
b).Milestone chart
c).Pie chart
d).None of these

Correct Answer:
Gantt chart
Explanation:



Q43). The earliest method used for planning of projects was

a).CPM
b).PERT
c).Bar chart
d).Milestone chart

Correct Answer:
Bar chart
Explanation:



Q44). Travel charts are used to

a).Analyse material handling
b).Determine inventory control difficulties
c).Plan material handling procedure and routes
d).All of the above

Correct Answer:
All of the above
Explanation:



Q45). PERT stands for

a).Programme estimation and reporting technique
b).Process estimation and review technique
c).Programme evaluation and review technique
d).Planning estimation and resulting technique

Correct Answer:
Programme evaluation and review technique
Explanation:



Q46). Actual performance of a task is called

a).An event
b).An activity
c).A duration
d).Any one of these

Correct Answer:
An activity
Explanation:



Q47). The start or completion of task is called

a).An event
b).An activity
c).A duration
d).Any one of these

Correct Answer:
An event
Explanation:



Q48). An activity requires

a).Events
b).Resources
c).Time and resources
d).Energy

Correct Answer:
Time and resources
Explanation: