Q33). The use of bar chart is very popular in construction departments because

a).It is very simple to prepare and interpret
b).Each item of work or activity is shown separately
c).Modification to the chart, if required, can be carried out easily
d).All of the above

Correct Answer:
All of the above
Explanation:



Q34). The chart which gives an estimate about the amount of materials handling between various work stations is known as

a).Flow chart
b).Process chart
c).Travel chart
d).Operation chart

Correct Answer:
Travel chart
Explanation:



Q35). the bar chart is also known as

a).Flow chart
b).Time chart
c).Travel chart
d).Gantt chart

Correct Answer:
Gantt chart
Explanation:



Q36). A bar chart is drawn for

a).Time versus activity
b).Activity versus resources
c).Resources versus progress
d).Progress versus time

Correct Answer:
Time versus activity
Explanation:



Q37). A drawback of the bar chart is that

a).All the activity are independent of each other
b).It is difficult to judge whether an activity is completed or not
c).The sequence of activities is not clearly defined
d).All of the above

Correct Answer:
The sequence of activities is not clearly defined
Explanation:



Q38). Which of the following statement is correct in bar chart planning?

a).The inter dependence of the operations can not be portrayed
b).The progress of work can be measured
c).The spare time of the activities can be determined
d).The schedule can not be updated

Correct Answer:
Both A. and D
Explanation:



Q39). A milestone chart

a).Depicts the delay of job
b).Shows the inter dependence of various jobs
c).Shows the events in chronological, but not in a logical sequence
d).All of the above

Correct Answer:
Shows the events in chronological, but not in a logical sequence
Explanation:



Q40). Milestone chart is an improvement over

a).Bar chart
b).PERT
c).CPM
d).All of these

Correct Answer:
Bar chart
Explanation: