500 Best Construction Management- MCQ

Q17). The contractor is responsible for

a).Procuring material which is not supplied by the owner
b).Organising and planning the work as per drawing
c).Executing the work as per specifications laid down in the contract
d).All of the above

Correct Answer:
All of the above
Explanation:



Q18). The resources in a construction project are made up of

a).Plant equipment and machinery required for the project
b).Construction materials such as cement, bricks, steel etc
c).Skilled and unskilled manpower
d).All of the above

Correct Answer:
All of the above
Explanation:



Q19). The pre-tender stage of construction requires

a).Selection of site
b).Acquisition of land
c).Finalisation of design
d).All of these

Correct Answer:
All of these
Explanation:



Q20). Technical planning is carried out for the

a).Preparation of detailed drawings
b).Preparation of detailed estimate
c).Planning resources and initiating procurement action
d).All of the above

Correct Answer:
All of the above
Explanation:



Q21). The post-tender stage of construction consists of

a).Assessment of work
b).Finalisation of accounts
c).Assessment of expenditure during execution
d).All of the above

Correct Answer:
All of the above
Explanation:



Q22). For the preparation of a construction schedule, the data required is

a).Number of operations
b).Number of activities
c).Output of labour
d).All of these

Correct Answer:
All of these
Explanation:



Q23). Military type of organisation is known as

a).Line organisation
b).Functional organisation
c).Line and staff organisation
d).None of these

Correct Answer:
Line organisation
Explanation:



Q24). In a line organisation

a).Discipline is strong
b).Quick decision are taken
c).Responsibility of each individual is fixed
d).All of these

Correct Answer:
All of these
Explanation: